Container unloading operations begins at Thilafushi Port with the arrival of MSS Galena, November 25, 2026. (Photo/Maldives Ports Limited)
Large cargo vessels have officially begun unloading laden containers at Thilafushi Port, marking another major milestone in the relocation of Male' Commercial Port operations.
The operation commenced on Wednesday with the arrival of the vessel MSS Galena, which transported 524 TEUs of cargo to the Maldives.
According to Maldives Ports Limited (MPL), 490 TEUs from the shipment are scheduled to be unloaded directly at Thilafushi Port.
MPL said the move is expected to ease congestion at Male' Commercial Harbour while supporting plans to fully relocate port operations to Thilafushi by November 2027.
The company previously began shifting services to Thilafushi as part of the relocation project, starting with container clearance operations at the Thilafushi Cargo Terminal. Wednesday's operation marks the start of laden container unloading at the new facility.
Today, laden container unloading operations commenced at Thilafushi Port with the arrival of MSS Galena. Of the 524 TEUs carried by the vessel to the Maldives, 490 TEUs are scheduled to be unloaded at Thilafushi Port. This initiative will ease congestion at Malé Commercial Harbour, as we work towards the full relocation of port operations to Thilafushi by November 2027. #mpl #portoftomorrow #maldivesportslimited #portmv #mplhidhumathugaa
— Maldives Ports Limited (@Portmv) November 25, 2026
The relocation project is intended to address longstanding space constraints at Male' Commercial Port and improve cargo handling efficiency, particularly as import volumes continue to grow alongside the expansion of the tourism industry and increased demand during peak periods such as Ramadan and the New Year season.
The new commercial port is expected to be significantly larger than the existing Male' port and is among the largest infrastructure projects currently underway in the Maldives.
As part of the development, the first 100 metres of the quay wall designated for domestic vessels has already been completed. MPL said around 40 percent of the backfilling work for the inner quay area has also been completed, while precast concrete blocks are being manufactured and preparations continue for the construction of terminal buildings.
China Harbor Engineering Company (CHEC) is constructing a 375-metre international quay wall with a depth of 14.6 metres.
The project is scheduled for completion by July next year. Once operational, the facility is expected to reduce vessel turnaround times to approximately two days.
Developed on 60 hectares of land, the port will initially have the capacity to handle 390,000 TEUs annually, with plans for future expansion to 1.8 million TEUs. The project also includes provisions to extend the international quay wall to 1.4 kilometres and construct more than two kilometres of quay facilities for domestic vessels.
Two ship-to-shore cranes and a mobile harbour crane are also scheduled to be installed when the port becomes operational.
MPL aims to complete the transfer of all Male' Commercial Port operations to Thilafushi by November next year and begin providing modernised port services, describing Wednesday's operation as a significant step towards achieving that goal.